Processing Authority: Measurement Department of Shanghai Quality and
Technical Supervising Bureau
Application Formality:
1. New examination
1) 2 copies of Measuring
Standard Assessing (Counterchecking) Application Form;
2) 1 Measuring
Standard Technical Report
3) 1 photocopy of Measuring Standard Survey
Repetitive Assessing Record
4) 1 photocopy of Measuring Standard Stability
Assessing Record
5) 1 photocopy of effectual testing certificate of standard
measuring instruments and major auxiliary equipments
6) 2 photocopies of
original record which meets the requirement of assessing projects and
corresponding simulative assessing certificate
2. Counterchecking
1) 2 copies of Measuring Standard Assessing
(Counterchecking) Application Form
2) Original version of Measuring Standard
Certificate
3) 1 photocopy of effectual testing certificate of standard
measuring instruments and major auxiliary equipments within the validity period
of Measuring Standard Certificate
4) 2 copies of Measuring Standard Changing
Application Form if the standard measuring instruments and major auxiliary
equipments are changed
5) At least 2 photocopies of original measuring
records of the standard measuring instrument (random sample) and assessing
certificate
6) 1 photocopy of Measuring Standard Stability Assessing Record
within the validity period of Measuring Standard Certificate
7) 1 photocopy
of Measuring Standard Survey Repetitive Assessing Record within the validity
period of Measuring Standard Certificate
8) 1 photocopy of operation
inspecting or assessing comparison record of the standard measuring instrument
between two periods.
Standard of counterchecking: The entity should apply for
counterchecking 6 months before the Measuring Standard Certificate is expired.
Otherwise, the entity need take procedures as new applications.
Processing Procedures:
1. The processing authority accept the
application;
2. The entrusted intermediary organization will take on the
assessing tasks. Normally, each project will have one measuring standard
examinant;
3. The examinant will provide assessing report and assessing
opinion;
4. The intermediary organization will audit the report and chop it,
then submit to the processing authority;
5. The processing authority audit
the assessing documents and make decisions;
6. Issue Measuring Standard
Certificate to the passer;
7. For the unqualified projects, the authority
will notify the applicant, explain the reason, and return all the applying
documents. For counterchecking projects, a cancellation procedure will be
taken.
Charging Standard & Basis:
1. Charging standard:
RMB 400 for each
item of the measuring standard assessing
RMB 120 for each item in
counterchecking
2. Basis:
Measuring Charging Items and Charging Standards
promulgated by State Quality and Technical Supervising Bureau, State Bureau of
Commodity Bureau, and the Ministry of Finance
Reporting Authority: Shanghai Quality and Technical Supervising Bureau
Processing Address: Room 1209, No. 1227 Chang-Le Road
Processing Basis:
1. The Metrology Law of the People's Republic of China
(approved on the 12th Standing Committee meeting of the 6th National People's
Congress on September 6th 1985, promulgated by Order No. 28 of the President of
the People's Republic of China);
2. Detail Rules for the Implementation of
the Metrology Law of the People's Republic of China (Approved by the State
Council on January 19, 1987 and promulgated by the State Measurement Bureau on
February 1, 1987 )
3. Shanghai Administrating Regulations on Measuring
Supervising (approved on the 22nd standing committee meeting of the 11th
Shanghai People's Congress on September 22nd 2000)
4. Rules of Measuring
Standard Assessing (promulgated by National Measurement Bureau on July 10th
1987)
5. Criterion of Measuring Standard Assessing (JJF 1033-2001,
promulgated by State Quality and Technical Supervising Bureau on March 2nd 2001,
implemented on June 1st 2001)
Contact Tel: 021-54045914
Processing Time: Monday to Friday 8:30-17:00
Time Limit for Processing: Finish the certificate issuing work within 120
working days after accepting the application. If there is need to countercheck
and restructure, the time limit will postpone.
Qualified Application Subject:
1. The measuring standard need be assessed
by authorized measurement assessing institution;
2. Has required environment
for normal work, i.e. the environment and workplace need be equipped with
required temperature, humidity, dustproof, shockproof, rotproof, and
anti-jamming;
3. Has employable staff with the conserving, maintenance and
bestowing job, i.e. the measuring assessing staff need have corresponding
certificate for his assessing item;
4. Has complete managing mechanism,
including preserving, maintenance, and bestowing mechanism of the measuring
standard, periodic assessing system, technical criterion and relevant technical
filings.
|