Registration of boiler using

[2008-12-23 16:54:10]

Processing Authority: Special Equipment Supervising Department of Shanghai Quality and Technical Supervision Bureau

Application Formality:

1. Basic requirements:

(1) The boiler should be produced by licensed manufacturer;

(2) The design of the stokehold shall be approved;

(3) The boiler should be installed by licensed enterprise;

(4) The boiler should be appraised to be eligible;

(5) Enough stokers are equipped.

2. Documents for application:

(1) Opinion paper on stokehold;

(2) Constructing registration form of the boiler installing enterprise;

(3) Boiler technology registration book (filled);

(4) Initial examining report of the boiler;

(5) Operating status examining report of the boiler;

(6) Water quality examining report of the boiler;

(7) Fuel (Gas) Boiler debug report;

(8) Water processing equipment debug report;

(9) Certificate of the stokers and water quality testing staff (copies);

(10) Relevant safety managing system of the enterprises that using boilers.

Processing Procedures:

1. After installing and appraising the boilers, the enterprise should make the registration procedures with relevant documents;

2. The processing authority audit the documents;

3. Take registration procedures and issue Boiler Using Registration Certificate.

Charging Standard & Basis:

Standard: RMB 5 for per certificate

Basis: Notice on Verifying Administration Charging Items and Standards of Shanghai Labor System by Shanghai Pricing Bureau and Shanghai Finance Bureau (Hu Jia She [1992] No. 177)

Processing Address:

Room 1005, 10th floor, No. 1227 Chang-Le Road

Processing Basis:

1. Interim Regulations on Safety Supervising of Boiler and Pressure Container

2. Rules on Safety Technology Supervising of Steam Boiler

3. Rules on Safety Technology Supervising of Hot Water Boiler

4. Rules on Safety Technology Supervising of Thermal Oil Heater

5. Rules on Safety Technology Supervising of Small Boiler and Normal Pressure Hot Water Boiler

6. Registration Regulations of Using Boiler

Contact Tel: 54049194、54045500×2003

Processing Time: Tuesday and Thursday 8:30-16:30

Time Limit for Processing: 1 working day for those who meet the requirements

Qualified Application Subject pressed boiler and normal pressure hot water boiler installed and bestowed in Shanghai.