License of designing and manufacturing boiler and pressure container

[2008-12-23 16:54:10]

Processing Authority: Special Equipment Supervising Department of Shanghai Quality and Technical Supervision Bureau

Application Formality:

I. Requirements of license for manufacturing D-Level boiler, and Class-1, Class-2 pressure container

1. Juridical person or organization authorized by juridical person;

2. With complete quality guarantee system of boiler and pressure container;

3. Has required technical power for the manufacture and management of boiler and pressure container;

4. Has producing facilities, testing equipments, and factories for the manufacturing requirements.

II. Requirements of license for designing Class-1 and Class-2 pressure container

1. Has legal representative or consigner;

2. Targeting the design of pressure container products, and adhere to the professional direction of products designing;

3. Has technical principals, checker, auditor, and designer for the pressure container product, while the staff number and proportion suiting the applying scope;

4. Has necessary designing equipment and measures, also equipped with computer designing facility;

5. Has special working organ and working place;

6. Has practical quality managing system and management mechanism;

7. Has certain designing experiences, with the ability to design the applied pressure container products independently.

III. Documents for application

1. Enterprise applying for boiler manufacturing license should submit an applying report and fill in the Boiler Manufacturing License Application Form.

2. Enterprise applying for pressure container designing license should submit Pressure Container Designing Qualification Application Form and self assessing report.

3. Enterprise applying for pressure container manufacturing license should submit the application report (2 copies), Pressure Container Manufacturing Application Letter, and Form of Company Basic Information and Major Equipment for Manufacturing Pressure Container.

4. Licensed enterprise to change license should make application to the license issuing authority 3 to 6 months before the due date. Or, it might make application before the end of February of the year which the license is matured.



Processing Procedures:

1. The processing authority make initial examination on the applying documents. The documents of the applicants that do not pass the initial examination will be returned. The applicants that pass the initial examination will receive a written notice of acceptance.

2. After receiving the notice of acceptance, the applicant shall make pilot design or manufacturing according to related standards and regulations. Normally, the amount of pilot designing is 10 units, while the pilot manufacturing is 1 to 2 units.

3. The entrusted intermediary organization will have fieldwork to assess the applicant and make assessing report forms.

4. The processing authority should audit the assessing reports and make decisions.

5. Issue Designing License or Manufacturing License to the eligible enterprise. For those unqualified enterprises, they need be restructured and make application again afterwards.

Charging Standard & Basis:

Standard: qualification appraising fee for D-Level boiler manufacturer is RMB 1,500

qualification appraising fee for Class-1 pressure container manufacturer is RMB 1,800

qualification appraising fee for Class-2 pressure container manufacturer is RMB 2,000

Basis: Notice on Verifying Administration Charging Items and Standards of Shanghai Labor System by Shanghai Pricing Bureau and Shanghai Finance Bureau (Hu Jia She [1992] No. 177)

Processing Address:

Room 1005 / Room 1006, No. 1227 Chang-Le Road

Processing Basis:

1. Interim Regulations on Safety Supervising of Boiler and Pressure Container and its detailed rules

2. Qualifications of Boiler Manufacturing License

3. Regulations on Supervising Pressure Container Designing Enterprise

4. Regulations on Qualification Cognizance and Supervising of Pressure Container Manufacturer

Contact Tel: 54049194、54046131

Processing Time: Boiler: Monday and Wednesday 8:30-16:30

Pressure Container: Tuesday and Thursday 8:30-16:30

Time Limit for Processing: finish the appraising work within 18 months after issuing the notice of acceptance. If the appraising work dose not be finished on time due to the applicant's reason, the notice of acceptance will invalidate immediately.

Qualified Applicant Subject:

D-Level boiler manufacturing license;

Class-1 and Class-2 pressure container designing license and manufacturing license.